Downtown DeLand Streetscape

Completed in 2000, the project spanned approximately 12 months. Covering approximately 2 miles, we worked on almost every aspect of both sides of the road. Streetlighting, traffic signalization, colored stamped concrete, brick pavers, landscape and irrigation, planters, sidewalks, eight intersections with colored stamped concrete, crosswalks, bulb outs, and landscape islands were all part of our scope of work.

Project Delivery Method:  Design-Bid-Build 